What we'll cover:
A good project is a project that delivers:
Human brain is not good at making estimates.
We all have cognitive bias
... cut it in consistent tasks.

Take three figures (points):
Estimation is a weighted average.
e = (b + 4m + w) / 6
And standard deviation
σ = (w − b) / 6
e = (2 + 4*4 + 10) / 6 = 4,666...
σ = (10 − 2) / 6 = 1,333...
Use SD to add confidence level:
You can estimate in group:
To estimate a project based on tasks estimation (e):
E = Σe
SD = √(Σσ^2)
The more subtasks you estimate, the more precise your project estimation will be.
Effort and costs are different from delay / planning
(but you have PERT to solve that)
and a thousand more...